Adani to complete 1,000 MW transmission line to Mumbai by Dec 2022

Image Source : PTI

Adani to complete 1,000 MW transmission line to Mumbai by Dec 2022

Adani Transmission Ltd (ATL) on Sunday affirmed that will probably be ready to execute a transmission line and sub-station mission at suburban Vikhroli which is able to improve the facility provide by 1,000 MW to the monetary capital, by the top of subsequent 12 months, as per the mandated deadline for it.

In a evaluate assembly taken following final Monday’s energy outage, Maharashtra Chief Minister Uddhav Thackeray had requested all stakeholders to expedite the mission by adhering to the timelines.

Trains had been caught on tracks, companies affected and do business from home staff impacted because the monetary capital plunged into darkness final Monday that lasted up to 14 hours in some pockets.

“Adani is committed to completing the Kharghar-Vikhroli transmission line project within the timeline set by Thackeray,” a spokesperson for Adani Group stated in a press release.

In the assertion, ATL stated there can be progress in energy load within the megapolis and the mismatch between technology and cargo progress, it’s now dedicated to executing two vital transmission initiatives that might assist channelise extra energy to Mumbai.

These capability enhancement initiatives will create an extra transmission capability of 1,000 MW every, thereby easing the present transmission corridors, it added.

It consists of the Kharghar-Vikhroli 400/220 kV EHV transmission line mission, which is able to add a 1,000 MW energy provide hall and also will be Mumbai’s first 400 KV Substation.

A current information report had stated that there was a dispute between Tata Power and ATL which has now been resolved with the previous agreeing to present land for the mission.

The mission was reportedly accredited in 2009 and awarded to ATL in 2019. ATL on Sunday stated it has already positioned orders for all vital gear and repair contracts, that are very important for mission completion, together with towers and insulators. It has additionally accomplished 80 per cent of engineering and is working with authorities to get possession of land parcels at Kharghar and Vikhroli.

Apart from the Vikhroli-Kharghar line, a second mission entails an 80-km hyperlink between Maharashtra State Electricity Transmission

Company’s (MSETCL) 400 kV Kudus & Adani Electricity Mumbai’s (AEML) 220 kV Aarey EHV Substation which can be a primary of its variety underground excessive voltage DC cabled system that may get an extra 1,000 MW of energy.

Adani has initiated land procurement, accomplished survey works, filed purposes for Regulatory, proper of approach and different statutory clearances, awarded consultancy contracts for system research and is within the means of elevating capital and finalizing awards for mission execution, the assertion stated. 